The stone dry hanging method can effectively avoid the hollowing, cracking, and falling of the board in the traditional wet pasting process, improve the safety and durability of stone buildings,At the same time, this method can keep the curtain wall clean and beautiful and avoid the whitening and discoloration of the board surface in the traditional wet-pasting process.
Prepare materials and tools.
Construction materials include stone, steel parts, steel keels, anti-rust paint, silver powder paint, AB glue, etc.
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
Construction tools include: laser level, ink fountain, electric welder, cutting machine, electric drill, air pump, vertical ruler, steel ruler, feeler gauge, endoscope, etc.
Construction steps
After the keel is welded, clean the welding slag and check the welding quality. The keel level height and weld quality should meet the specifications and design requirements.
4.Three steps for keel acceptance
The keel can be said to be the most basic and important part of Zhengge dry hanging stone craftsmanship. Then, the acceptance of welded keels is particularly critical.

- When accepting keels, they should be accepted according to the construction drawings, and the verticality of the vertical keel installation and the horizontality of the horizontal keel should be checke
- Before the dry-hanging stone accident occurs, check the position and quantity of the embedded parts on the main structure of the wall.
- Check the connection of the embedded parts of the main structure (including the connection between the embedded parts of the front dry-hanging stone wall and the adapter, the connection between the adapter and the vertical purlin, and the connection between the vertical purlin and the horizontal purlin).
After the keel is inspected, the welding parts are evenly painted with two coats of anti-rust paint, and the silver powder paint is applied after the anti-rust paint is completely dry.
5. Stone dry-hanging link
After the overall concealment of the keel is inspected, the stone dry-hanging link begins.

(1) Stone grooving
Before the stone enters the factory, six sides must be protected and qualified after inspection. The must not be damaged or collapsed during the grooving process.
Temporarily fix the stone and groove the upper and lower sides of the stone at the designed position. The length is 60-80 mm and the width is 6-7 mm.
The designed stone position must be centered.
For this kind of stone with close joints, a notch is reserved according to the thickness of the hanger after the groove is cut.
The depth of the groove and the notch must ensure that the hanger is completely embedded.
The single-sided groove should be polished to a 45° chamfer for easy hooking.
The groove should be clean, and the stone chips in the groove should be removed.

(2). Hanger and stone installation
Temporarily fix the housekeeper with bolts at the punched hole of the horizontal keel with the nut facing up.
At the same time, place the flat washer and spring washer completely and tighten them appropriately.
If the position is not consistent, adjust the hanger.
Refer to the installation control line, check the flatness and verticality, and adjust the hanger. Determine
the hanger position and notch depth according to the subsequent installation requirements.
Apply the mixed AB glue to the lower groove , into the hanger and level it.
Also, apply AB glue to the upper groove of the stone, insert the upper hanger support plate groove,
and tighten the fixing nut. The exposed threads of the bolts should be no less than 2.
After completion, check the flatness and verticality of the stone surface, check whether the joint gaps between adjacent stones are straight and whether there are any
height differences. If any non-compliance is found, it should be corrected in time.
6. Finished product acceptance