The stone dry hanging method can effectively avoid the hollowing, cracking, and falling of the board in the traditional wet pasting process, improve the safety and durability of stone buildings,At the same time, this method can keep the curtain wall clean and beautiful and avoid the whitening and discoloration of the board surface in the traditional wet-pasting process.

Prepare materials and tools.

Construction materials include stone, steel parts, steel keels, anti-rust paint, silver powder paint, AB glue, etc.

6 steps to dry hanging stone wall installation
stone

6 steps to dry hanging stone wall installation
AB glue

6 steps to dry hanging stone wall installation
Steel keel

6 steps to dry hanging stone wall installation
Steel parts

6 steps to dry hanging stone wall installation
Anti-rust paint

6 steps to dry hanging stone wall installation
silver powder paint

Construction tools include: laser level, ink fountain, electric welder, cutting machine, electric drill, air pump, vertical ruler, steel ruler, feeler gauge, endoscope, etc.

Construction steps

1. On-site layout

First, we need to measure and mark the 50-cm elevation line of the building,

the wall finish line and other reference lines, and the positioning line of the

keel according to the 1-meter elevation line of the main building.

6 steps to dry hanging stone wall installation
On-site layout

6 steps to dry hanging stone wall installation
Installation of keels

2. Installation of keels

First, the embedded wire installation should be completed before the keel is welded.

The embedded parts installation position should be determined according to the position

relationship between the embedded parts and the keel in the construction drawings,

3. Installation of keel welding

The height and length of the weld should meet the requirements of the specifications. Weld the vertical keel according to the embedded parts positioning position; install and weld the wall transfer keel.

Bolt the transfer keel firmly to the vertical keel, and weld the horizontal keel to the vertical keel according to the grid line position of the drawing. Before welding the horizontal keel, holes should be punched in advance according to the stone size and the position of the hanger. The hole diameter should be 1-2 mm larger than the bolts for fixing the hanger to facilitate the left and right adjustment of the hanger.

6 steps to dry hanging stone wall installation
Installation of keel welding

 

After the keel is welded, clean the welding slag and check the welding quality. The keel level height and weld quality should meet the specifications and design requirements.

4.Three steps for keel acceptance

The keel can be said to be the most basic and important part of Zhengge dry hanging stone craftsmanship. Then, the acceptance of welded keels is particularly critical.

6 steps to dry hanging stone wall installation
Acceptance of keels
  • When accepting keels, they should be accepted according to the construction drawings, and the verticality of the vertical keel installation and the horizontality of the horizontal keel should be checke
  •  Before the dry-hanging stone accident occurs, check the position and quantity of the embedded parts on the main structure of the wall.
  •  Check the connection of the embedded parts of the main structure (including the connection between the embedded parts of the front dry-hanging stone wall and the adapter, the connection between the adapter and the vertical purlin, and the connection between the vertical purlin and the horizontal purlin).

After the keel is inspected, the welding parts are evenly painted with two coats of anti-rust paint, and the silver powder paint is applied after the anti-rust paint is completely dry.

 

 

5. Stone dry-hanging link

After the overall concealment of the keel is inspected, the stone dry-hanging link begins.                                                   

6 steps to dry hanging stone wall installation
grooving

 (1) Stone grooving

Before the stone enters the factory, six sides must be protected and qualified after inspection. The  must not be damaged or collapsed during the grooving process.

Temporarily fix the stone and groove the upper and lower sides of the stone at the designed position. The length is 60-80 mm and the width is 6-7 mm.

The designed stone position must be centered.

For this kind of stone with close joints, a notch is reserved according to the thickness of the hanger after the groove is cut.

The depth of the groove and the notch must ensure that the hanger is completely embedded.

The single-sided groove should be polished to a 45° chamfer for easy hooking.

The groove should be clean, and the stone chips in the groove should be removed.

 

6 steps to dry hanging stone wall installation
Hanger and stone installation

(2). Hanger and stone installation

Temporarily fix the housekeeper with bolts at the punched hole of the horizontal keel with the nut facing up.

At the same time, place the flat washer and spring washer completely and tighten them appropriately.

If the position is not consistent, adjust the hanger.

Refer to the installation control line, check the flatness and verticality, and adjust the hanger. Determine

the hanger position and notch depth according to the subsequent installation requirements.

Apply the mixed AB glue to the lower groove , into the hanger and level it.

Also, apply AB glue to the upper groove of the stone, insert the upper hanger support plate groove,

and tighten the fixing nut. The exposed threads of the bolts should be no less than 2.

After completion, check the flatness and verticality of the stone surface, check whether the joint gaps between adjacent stones are straight and whether there are any

height differences. If any non-compliance is found, it should be corrected in time. 

6. Finished product acceptance

6 steps to dry hanging stone wall installation
Finished product acceptance

6 steps to dry hanging stone wall installation
Finished product acceptance
Finished product acceptance is mainly divided into apparent quality and physical quality.

The acceptance of finished products is mainly divided into apparent quality and physical quality.

The apparent quality can be checked by visual observation and touching the appearance of the stone.

There are no cracks on the surface, no scratches greater than 100 mm are allowed, and no more than

8 minor scratches less than 100 mm per square meter.

Use a steel ruler to check the width and straightness of the joints.

Use an endoscope to check the fullness of the AB glue applied on the back of the wall.

6 steps to dry hanging stone wall installation
Finished product acceptance

6 steps to dry hanging stone wall installation
Finished product acceptance
 

Measure the verticality, flatness, and verticality of the surface, and control the deviation value within 2 mm.

Measure the height difference of the stone joints, and the deviation value should be controlled within 0.5–1 mm.

HRST STONE(CENTURY STAR)Marble show

6 steps to dry hanging stone wall installation
                             Caribbean Island Marble

6 steps to dry hanging stone wall installation
                                        Clivia Marble

6 steps to dry hanging stone wall installation
                                   Brown Wooden Marble